News from the Nakhodka ship repair yard

«At the first three crab vessels, the pulling cable, the remaining ship systems are installed and deck fittings are installed. At the final stage, insulating work, the formation of partitions for cabins and other spaces. All major equipment has been loaded onto the vessels and its final installation and connection is being carried out, » said Alexander Gabriel, chief constructor of the Antey Group.

Three more vessels are at the outfitting slipways: 032,033,034. Hangers are installed on them for ship systems and cable ladders. Technological cutouts for equipment loading have already been made. In addition, work is underway to manufacture deck fittings: covers, manholes, ladders, etc.

At the same time, sections and blocks are being made to form the hulls of two more crab vessels with building numbers 035, 036.